Project background
The walkway is 400m long and situated along the Victoria Wharf, adjacent to the Titanic HBO Studios facility.
What was involved?
The works included:
- site clearance
- protecting and diverting existing electrical cables and water supply pipes
- trenching and ducting for new electrical cables and lighting
- laying and compacting of stone fills
- construction of reinforced concrete foundations
- erection of new railings and stone fencing
- landscaping works
- provision of street furniture and signposts
The works overlapped with a separate project to install a feature lighthouse optic light, and landscaping at the northern corner of the site.